8/28/17
Since the project was approved in 2012, the Sanitation Districts of Los Angeles County has been working on the tunnel design. That has also entailed conducting soil investigations along the tunnel alignment so that they have a good geological profile. The current schedule is:
- 2017 – Finalize Engineering Design, Obtain Permits & Rights-of-Way
- 2018 – Begin Construction at JWPCP (Carson)
- 2020-2024 – Tunneling
- 2023-2025 – Work at Royal Palms Beach
There is a public workshop scheduled for September 19 @ 6:30 pm at the San Pedro DoubleTree Hotel.
The contact person is:
Glenn Acosta
GLENN ACOSTA, P.E. | Senior Engineer | Public Information Office | 562.908.4288 x2304
SANITATION DISTRICTS OF LOS ANGELES COUNTY | 1955 Workman Mill Road, Whittier CA 90601